Rockaway Project Resumes as Crews Increase Efforts

Published Nov. 9, 2020
Updated: Nov. 9, 2020
Col. Luzzatto visits Rockaway

Colonel Matthew Luzzatto, Commander, New York District, is briefed on progress at the Rockaway project in Rockaway NY.

Crews resume work at Rockaway.

Crews resume beach work at Rockaway.

Lt. Gen. Scott A. Spellmon, Chief of Engineers, visited New York District.

Lt. Gen. Scott A. Spellmon, Chief of Engineers, visited New York District to oversee work beginning on the Rockaway Project in Rockaway New York.

Rockaway, NY -  Beach work on the Rockaway Peninsula is in full swing as the long-awaited East Rockaway Inlet to Rockaway Inlet, and Jamaica Bay Project gets underway in Rockaway, New York. There has been an authorization for the project since 1965, the Rockaway shoreline has experienced severe hurricanes and northeasters over the last 40 years. In 1960 Hurricane Donna caused $8,774,000 (1960 price level) in damages, including 6,000 homes and hundreds of commercial establishments and  1962 another storm inflicted $8,450,400 (1962 price level) in damages to the Rockaway Peninsula.

After Hurricane Sandy Congress allocated more funds to construct a project on the Rockaway Peninsula, and a Beach replenishment project was performed shortly thereafter. In May of 2019 the Corps and the City of New York laid an additional 348,000 cubic yards of sand at Rockaway Beach to replace lost sand due to heavy erosion after back-to-back nor’easters in March of 2019.

The larger main-construction project is currently underway, and Contract 1 consists of multiple beach improvements for Rockaway. This contract was awarded in June of 2020 to H&L Contracting LLC for the amount of $113.9M. Two types of armor stone are being delivered to the beach here in Rockaway to prepare for the beginning of groin construction. Groins are stone structures that are meant to slow down natural beach erosion. Rockaway will be getting 14 new groins, while 5 others will be refurbished, in continuing efforts to further protect the peninsula and reduce coastal storm risk. The remains of aging timber piers along the project area will also be removed.

The groins will be made up of armor stone. Type B armor stone is typically 3-7 tons, while type A armor stone is 7-12 tons. Both types of armor stone are being excavated from quarries in New Jersey. Bedding stone will also be used as a foundation for the groins with core stones lining the inside of the groins. The groins will finally be capped off with type A and B armor stones.

Two 1250 Rock Handling Excavators are placing the armor stones along the project area along with a 374 Excavator with a bucket that will move sand. There is a haul truck that is bringing armor stone to the staging area for the groins along with a front-end payloader that loads the hauler.
The beaches are currently closed in 500-600 foot sections in order to allow work to continue as well as not to restrict access to the beach during this mild fall season. More closures are expected this winter season as work continues on the groins. Groin work is expected to resume until March or April of 2021, then the next phase. Contract 2, which will begin and consist of a reinforced dune construction, and pedestrian beach crossovers made of timber structures for beach access spanning the new dunes for access from the boardwalk to the beach.  More sand placement in a later Contract 3 will occur as well as  Jamaica Bay side improvements which are currently in the design phase.

This project is being constructed in coordination with the City of New York, The New York State Department of Environmental Conservation, the National Park Service, and NYC Parks.