  • Telle navigates infrastructure modernization strategy with TVA at Wilson Lock

    FLORENCE, Ala. (July 27, 2026) – Aimed at strengthening the Tennessee River's vital commercial corridor, Assistant Secretary of the Army for Civil Works Adam R. Telle toured Wilson Lock last week to review navigation operations and discuss collaborative infrastructure modernization strategies with the Tennessee Valley Authority.
  • USACE terminates Chickamauga Lock Chamber Contract

    NASHVILLE, Tenn. (May 8, 2026) – The U.S. Army Corps of Engineers (USACE) Nashville District terminated the lock chamber contract with Shimmick Construction Company, Inc. (SCCI), at the Chickamauga Lock Replacement Project on the Tennessee River in Chattanooga, Tennessee, effective today. This decisive action is necessary to get the project back on track and protect taxpayer dollars.
  • Engineer performing surgical overhaul of Wilson auxiliary lock recounts career path

    NASHVILLE, Tenn. (Feb. 25, 2025) – When the Wilson Lock’s main chamber went offline last year, the Tennessee River’s heartbeat depended entirely on its aging auxiliary system. To keep barge traffic moving, U.S. Army Corps of Engineers crews worked around the clock to maintain the "double lift" lockage. Today, that marathon continues as Mechanical Engineer Peter McDonald and his team return to the auxiliary lock for a surgical overhaul. The mission: replacing critical hydraulic cylinders and the complex web of piping, pins, and A-frame assemblies that power the lock's massive filling and emptying valves.
  • USACE awards Chickamauga Lock Replacement Project’s final contract

    NASHVILLE, Tenn. (Feb. 13, 2026) – The U.S. Army Corps of Engineers Nashville District announces the award of the Approach Wall and Decommissioning Contract yesterday to C.J. Mahan Construction Company LLC. This is the final contract to complete the Chickamauga Lock Replacement Project at Tennessee River mile 471 in Chattanooga, Tennessee.
  • Rare historic footage surfaces of 1961 Wheeler Lock collapse

    ROGERSVILLE, Ala. (Sept. 15, 2025) – A forgotten piece of motion picture history recently surfaced from a retired U.S. Army Corps of Engineers operations manager for the Tennessee River. Jim Davis, who served in the Nashville District from 1968 to 2014, discovered an old Kodachrome movie in his family’s possession containing unseen footage of the wall collapse at Wheeler Lock in 1961.
  • Wilson Lock expected to reopen soon

    FLORENCE, Ala. (June 26, 2025) – The U.S. Army Corps of Engineers Nashville District officials report that Wilson Lock at Tennessee River mile 259.4 is expected to reopen on or about June 30, 2025. 
  • Miter gate installation begins at Chickamauga Lock

    CHATTANOOGA, Tenn. (April 18, 2025) – The U.S. Army Corps of Engineers Nashville District, in partnership with Shimmick Construction and Tennessee Valley Authority, recently began erecting massive miter gates for the Chickamauga Lock Replacement Project. This milestone brings the project closer to its goal of enabling both recreational vessels and commercial barges to pass through the new lock chamber, a critical step in modernizing regional infrastructure.
  • Congressman responsible for improving water resources infrastructure visits locks

    NASHVILLE, Tenn. (April 1, 2025) – Whether or not the Corps of Engineers constructs a brand-new navigation lock or operates and maintains one well into its designed lifespan, these critical infrastructure projects require significant appropriations and receive a great deal of Congressional interest and oversight.
  • USACE hosts prospective contractors for Chickamauga Lock home stretch

    The U.S. Army Corps of Engineers Nashville District hosted a pre-proposal site visit on March 4, providing potential contractors with a detailed look at the Chickamauga Lock Replacement Project prior to bidding on the final contract to complete the new lock.
  • Wilson Lock reopening now planned for June 2025

    The U.S. Army Corps of Engineers Nashville District has revised the timeline for completion of repairs to the main chamber of Wilson Lock near Florence, with reopening of the lock now estimated in June 2025.