Results:
Tag: Wolf Creek Dam
Clear
  • Nashville District completes Wolf Creek Dam barrier wall

    JAMESTOWN, Ky. (March 6, 2013) – Construction workers placed concrete for the last pile today, which completes the underground barrier wall and paves the way for raising the Lake Cumberland pool level. It is the last of 1,197 piles that are approximately four feet in diameter and extend 275 feet from near the top of the dam into bedrock below the foundation of the 4,000-foot long embankment of Wolf Creek Dam.
  • Wolf Creek Dam project officer promoted to captain

    JAMESTOWN, Ky. (Jan. 11, 2013) – The commander of the U.S. Army Corps of Engineers Nashville District promoted a first lieutenant assigned to the Wolf Creek Foundation Remediation Project today during a ceremony at the resident engineer office.
  • NR 12-046: Nashville District announces plans to tighten restrictions around Corps Dams

    NASHVILLE, Tenn. – The U.S. Army Corps of Engineers Nashville District is finalizing plans to implement 24/7 restricted waterborne access to hazardous waters immediately upstream and downstream of all Corps-owned locks and dams, flood control dams and multipurpose dams on the Cumberland River and its adjoining tributaries. This action moves the Nashville District into full compliance with Corps regulations.
  • Nashville District names its employee of the month for August 2012

    NASHVILLE, Tenn. (Oct. 24, 2012) - John Schnebelen, safety technician at Wolf Creek Dam’s Resident Engineer Office, is the U.S. Army Corps of Engineers Nashville District Employee of the Month for August 2012.
  • Burcham tours one of Nashville District’s major rehabilitation projects

    JAMESTOWN, Ky. (Oct. 10, 2012) – The U.S. Army Corps of Engineers Nashville District welcomed Brig. Gen. Margaret W. Burcham, Great Lakes and Ohio River Division commander, on her first visit to Wolf Creek Dam’s Foundation Remediation Project.
  • Work crews reach million-hour safety milestone at Wolf Creek Dam

    Construction crews at the Wolf Creek Dam Foundation Remediation Project reached a lofty safety milestone today when the men and women installing a concrete barrier wall deep into the dam's embankment reached 550 days and one million work-hours on the job without a lost-time accident.
  • Work crews reach million-hour safety milestone at Wolf Creek Dam

    JAMESTOWN, Ky. (Aug. 17, 2012) – Construction crews at the Wolf Creek Dam Foundation Remediation Project reached a lofty safety milestone today when the men and women installing a concrete barrier wall deep into the dam’s embankment reached 550 days and one million work-hours on the job without a lost-time accident.
  • Nashville mayor goes up river to see dam safety project

    Nashville Mayor Karl Dean visited Wolf Creek Dam Aug. 7, 2012 to see the ongoing foundation remediation construction, which is a dam safety project of vital importance to the citizens he represents 270 miles downstream.
  • Nashville mayor goes up river to see dam safety project

    JAMESTOWN, Ky. (Aug. 7, 2012) – Nashville Mayor Karl Dean visited Wolf Creek Dam today to see the ongoing foundation remediation construction, which is a dam safety project of vital importance to the citizens he represents 270 miles downstream.
  • Higher headquarters observes how Cumberland River Basin supported Greater Mississippi River System during 2011 flood fight

    NASHVILLE, Tenn. (July 27, 2012) – When the lower Ohio and Mississippi Rivers experienced a flood of record in the spring of 2011, the U.S. Army Corps of Engineers Nashville District supported the flood fight by holding back water at its dams in the Cumberland River Basin reservoir system.