U.S. Army Corps of Engineers announces publication of 2026 nationwide permits
Jan. 08, 2026 | 
News Release
The U.S. Army Corps of Engineers announced today the publication of the 2026 nationwide permits in the Federal Register. The 56 reissued and one new...
Read More
U.S. Army Corps of Engineers announces finalization of nationwide permits
Jan. 07, 2026 | 
News Release
The U.S. Army Corps of Engineers announced today that it will reissue 56 existing nationwide permits and issue one new permit for work in wetlands and...
Read More
A Soldier and three other civilian men document events in an airfield tower.
USACE Black Start Exercise Brings Light to Readiness
Nov. 20, 2025 | 
News
Increased installation readiness is the goal of the Black Start Exercise Program, a joint U.S. Army Corps of Engineers-led initiative, to test and...
Read More
Army Executes POTUS Directive on Ambler Road Project
Oct. 23, 2025 | 
News Release
President Donald J. Trump has approved the appeal of the Alaska Industrial Development and Export Authority (AIDEA), directing the U.S. Army Corps of...
Read More
USACE introduces new Regulatory Request System module
Sep. 22, 2025 | 
News Release
The U.S. Army Corps of Engineers announced today the launch of a new “No Permit Required” module on its Regulatory Request System (RRS), an innovative...
Read More
Army Corps of Engineers begins implementing policy to increase America’s energy generation efficiency
Sep. 22, 2025 | 
News Release
Assistant Secretary of the Army for Civil Works Adam Telle today directed the U.S. Army Corps of Engineers to weigh whether energy projects that might...
Read More

HQ USACE News

White River Backwater Levee Gravel Resurfacing a success

Published March 12, 2021
IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

Imagine it’s pouring rain for days on end, and you live near the Mississippi River. Not a far-fetched idea for many. With rain comes rising river waters and possible flooding. To prepare for such events, monitoring the river is essential but much harder to do if the levee surface isn’t safe for travel. That’s why projects like this one are important to the people living near and around the White River Backwater Levee.

Congratulations to the Memphis District and our Project Partner, the White River Drainage District for completing the White River Backwater Levee Gravel Resurfacing Project in Phillips County, Arkansas, on Feb. 10, 2021.

This completed construction milestone was a 15-mile gravel resurfacing project completed by A-Rock Construction. 2019 flood damage supplemental funds paid for the project.

“The maintenance of the levee crown is important to maintain a safe and effective means of monitoring levee conditions during flooding events, as stated earlier,” Project Manager Jairus Stroupe said. “Additionally, it protects the levee to prevent damages from ponding water and excessive traffic. This levee roadway section is also vital to long-haul trucks providing fuel to the Graham Burke Pumping Plant.”

Without these pumps operating at full capacity, more than 150,000 acres in the White River Levee and Drainage District and the citizens living there would be at risk during high water events.

The Project Delivery Team members responsible for seeing this project through to completion are Project Manager Jairus Stroupe, Technical Lead Biobaragha Dambo, GIS Engineer -- Lindsey Barrios, Contracting Specialist Sequoria Wilson, Real Estate Specialist John Green, Cost Engineer Conrad Stacks, and contract oversight and administration by the Wynne Area Office.  


News/News Release Search

@USACEHQ

Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
Twitter
Logo
X
46,742
Follow Us

News Releases

White River Backwater Levee Gravel Resurfacing a success

Published March 12, 2021
IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

IN THE PHOTO, A Rock Construction works to resurface the levee crown near Phillips County, Arkansas. 2019 flood damage supplemental funds funded the project.

Imagine it’s pouring rain for days on end, and you live near the Mississippi River. Not a far-fetched idea for many. With rain comes rising river waters and possible flooding. To prepare for such events, monitoring the river is essential but much harder to do if the levee surface isn’t safe for travel. That’s why projects like this one are important to the people living near and around the White River Backwater Levee.

Congratulations to the Memphis District and our Project Partner, the White River Drainage District for completing the White River Backwater Levee Gravel Resurfacing Project in Phillips County, Arkansas, on Feb. 10, 2021.

This completed construction milestone was a 15-mile gravel resurfacing project completed by A-Rock Construction. 2019 flood damage supplemental funds paid for the project.

“The maintenance of the levee crown is important to maintain a safe and effective means of monitoring levee conditions during flooding events, as stated earlier,” Project Manager Jairus Stroupe said. “Additionally, it protects the levee to prevent damages from ponding water and excessive traffic. This levee roadway section is also vital to long-haul trucks providing fuel to the Graham Burke Pumping Plant.”

Without these pumps operating at full capacity, more than 150,000 acres in the White River Levee and Drainage District and the citizens living there would be at risk during high water events.

The Project Delivery Team members responsible for seeing this project through to completion are Project Manager Jairus Stroupe, Technical Lead Biobaragha Dambo, GIS Engineer -- Lindsey Barrios, Contracting Specialist Sequoria Wilson, Real Estate Specialist John Green, Cost Engineer Conrad Stacks, and contract oversight and administration by the Wynne Area Office.  


Mississippi Valley Division