In one of the most logistically-challenging renovations the district has seen, the U.S. Army Corps of Engineers Louisville District helped to complete the monumental task of renovating 260,000 square feet in over 41 departments throughout the Wright-Patterson Air Force Base Medical Center Complex in Ohio—all with minimal impacts to patient care.
Wright-Patt hospital renovation improves patient care
9/2/2015 8:59:00 AM
Testing and balancing technician set-up to measure flow rate and temperature of the fluid. This typically occurs during the construction phase of the commissioning process.
Water-side test and balance set-up
8/31/2015 5:56:00 PM
Pre-funtional check-out and visual inspection of the blower motor and thermostat positioning. This typically occurs during the construction phase of the commissioning process.
Inspecting a blower and thermostat installation
8/31/2015 5:54:00 PM
Pre-functional check-out of rooftop air handler. This typically occurs during the construction phase of the commissioning process.
Inspection of rooftop air handler
8/31/2015 5:51:00 PM
Performance Verification Test (PVT) on a new control panel in a building at Fort Campbell. This typically occurs during the construction phase of the commissioning process.
Performance verification test on a control panel
8/31/2015 5:49:00 PM
Pump pressure gauges are read and then the corresponding flow is determined from the pump manufacturers curve. This typically occurs during the acceptance phase of the commissioning process.
Pump performance validation
8/31/2015 5:46:00 PM
Measuring differential pressure to be used to calculate terminal airflow. This typically occurs during the construction phase of the commissioning process.
Differential pressure gauge
8/31/2015 5:42:00 PM
This open office faces south with horizational exterior sun shades to provide passive sun control. A clearstory above captures northern daylight to maximize consistent daylight throughout the day. The result was a staggering 94% achieved daylghting in this space in accordance with the caluclaiton methods defined by LEED NC 2009. Team Members included Kyle Shaw, Nathan Gregory, Jennifer Ramirez, Lindsey Matetich, David Chapman, Kevin Waring, Gerd Padilla, David Wong, Allen Heninger, Cynthia Masten, and Rod Perry.
Battalion Headquarters Open Office at Joint Base Lewis-McChord
8/28/2015 4:43:00 PM